Well Spring Estate
Two packages for one estate: a new 1MVA transformer with its 33kV and 11kV protection brought back into service, then the estate's 33kV line and distribution network rehabilitated end to end.
- Location
- Idishi, Jericho, Ibadan, Oyo State
- Rating
- 1MVA2.5km 33kV300 + 500kVA2 RMUs

Scope delivered
Installation of a 1 × 1MVA, 33/11kV transformer; rehabilitation of the 33kV outdoor breaker and 11kV indoor breakers with tripping unit and transformer control panel. Rehabilitation of 2.5km of 33kV line and servicing of 300kVA and 500kVA transformers, two ring main units and feeder pillars.
Package A
- Installation of 1 × 1MVA, 33/11kV transformer
- Rehabilitation of 33kV outdoor breaker
- Rehabilitation of 11kV indoor breakers, with tripping unit and transformer control panel
- 33kV isolator relocated
Package B
- Rehabilitation of 2.5km of 33kV line
- Servicing of 300kVA and 500kVA, 11/0.415kV transformers
- Servicing of 2 Nos ring main units (RMUs) and feeder pillars